Client: Hitachi India
End User: Narmada Valley Development Authority (NVDA)
Location: Nagalwadi, Madhya Pradesh
Project Duration: 2021-2022
Scope: Design, Engineering, Manufacturing, and Supply of Switchyard Structures
Vijay Transmission Private Limited (VTPL) executed a comprehensive turnkey supply solution for the NVDA Nagalwadi substation project, encompassing:
VTPL’s engineering team developed the entire structural design and layout from the ground up, demonstrating our in-house capabilities in:
Working closely with Hitachi India, VTPL managed the complete supply chain from conceptualization to delivery. Our team coordinated seamlessly across design, production, and logistics functions to meet project timelines. The structures were manufactured to exacting specifications, galvanized for corrosion resistance, and delivered ready for installation.
The project achieved successful commissioning by 2022, with all VTPL-supplied structures performing to specifications. This milestone reinforced NVDA’s power infrastructure in Madhya Pradesh, contributing to enhanced electricity distribution capacity in the region.
This project showcased VTPL’s comprehensive capabilities as a design-to-delivery partner for critical power infrastructure projects. Our ability to handle complete engineering responsibility while maintaining quality and timeline commitments positioned us as a trusted supplier for major EPC contractors like Hitachi India.